Port Washington's North-Side Traffic Fixes Are Built to Come Down. Here's What's Out There Until 2028.

The temporary signals that started working at I-43 Exit 100 on Wednesday, September 2, are not a permanent new intersection for Port Washington's north side. The signals, the wider ramps, the wider turns on Highland Lane and the new turn lanes on Lake Drive were all built for construction traffic to the Vantage Data Centers Lighthouse Campus. "These improvements will actually be removed when construction (of the data center) is complete," Graef engineer Alex Motl told the Common Council, as Ozaukee Press reported in April.

So the road layout you drive past Highway LL today is a construction-era layout. It was sized for one number, and Vantage projected its workforce would reach that number by mid-October.

The Layout Was Drawn Around 5,000 Workers

The campus covers 672 acres on the city's north side. Plans call for four single-story buildings totaling 2.5 million square feet, finished in 2028 and used by Oracle and OpenAI. As early as April, City Engineer Roger Strohm described the traffic as up to 5,000 construction workers plus trucks hauling large, heavy loads to the site.

The workforce built up in stages:

Date reported Workers on site Source
Early May 2026 About 500, per a Town of Port resident speaking to the Common Council Ozaukee Press, May 6
Mid-September 2026 About 3,200, per Vantage Ozaukee Press, Sept. 16
Mid-October 2026 Roughly 5,000 projected, per Vantage Ozaukee Press, Sept. 16
After the 2028 opening About 1,000 long-term jobs, per Oracle Ozaukee Press, Sept. 16

That last row is the reason the hardware is temporary. A campus with about 1,000 permanent staff doesn't need roads built for five times that many. The 5,000 figure was Vantage's projection in September, not a confirmed count, but the design logic holds either way. The temporary intersections are built for the construction crowd, and the permanent campus will create far less traffic.

Where the Temporary Pieces Sit

Here's what Graef's plan put on the ground, based on the April presentation and the county agreement the Common Council approved in June:

  • I-43 at Highways 32 and H, Exit 100: temporary traffic signals on the ramps, timed with the existing light at Wisconsin Street and Highway LL so traffic doesn't back up onto the freeway. The ramps are also being widened.
  • Highland Lane at Highland Drive, and Highland Lane at Highway LL: wider lanes and a bigger turning radius.
  • Lake Drive at Highways KW and LL: added turn lanes and a wider turning radius.
  • Ozaukee Interurban Trail crossings at Highland and Lake drives: plans called for rapid flashing beacons that bicyclists can trigger to warn drivers.

Strohm put the number of intersections to be widened at about five, with each one taking about a week and bringing lane closures or flaggers while the work was underway. "We want to get construction traffic out of the traffic lanes," Motl said, according to Ozaukee Press. The turn lanes exist to give a dump truck somewhere to wait without blocking a car behind it.

The Fixes Kept Landing After the Traffic

The lights at Exit 100 are a good way to see how the project's road work has lined up with its workforce. Each update pushed the start date out, while the head count kept climbing.

  1. April 15: Ozaukee Press reported that the road work would be done "in the coming month or two." No firm timeline had been set.
  2. June 17: The city was still waiting on state Department of Transportation permits. Strohm expected the signals to go in by mid-July.
  3. August 19: The lights were expected the following week, maybe as early as Monday, August 24.
  4. September 2: The signals started working after 9 a.m., according to Vantage's construction updates page.

By the time Vantage gave a count at its September 10 event, about 3,200 workers were on site. Six days after the lights went live, on September 8, crews started widening the Highway LL turn lanes near Highland, with flaggers and single-lane traffic. Some of the work meant to ease traffic added its own delays while the workforce was still growing.

Strohm never presented the lights as a full fix. "I've been there at shift change and yes, it's crazy," he said in Ozaukee Press's August report. He added that signals can't do anything about the sheer volume of traffic. They can control the peaks and should end the need for police to direct traffic at the ramps.

What the Peak Hours Have Looked Like

Before the signals, the busiest hours were easy to spot from where the officers stood. In May, Ozaukee County Sheriff Christy Knowles told the Common Council that Vantage had contracted, at its own cost, with her office and the Wisconsin State Patrol for weekday traffic control from 5:30 to 7:30 a.m. and 3:30 to 5:30 p.m., Ozaukee Press reported. Officers worked three spots:

  • Highways D and LL in Belgium, where traffic from the north leaves the freeway
  • The I-43 ramps on Port's north side, where traffic from the south gets off
  • Lake Drive and Highway KW in the Town of Port

Those were traffic-control hours, not a published shift schedule, and they date from a time when about 500 workers were on site. Knowles also said she had waited six minutes to cover six-tenths of a mile on Highway LL. One caller told her the drive from Port to Belgium took 40 minutes. She singled out trucks turning north from Lake Drive onto Highway LL as especially hard, because the drivers have to inch out to see oncoming traffic.

That same turn came up again at Vantage's "community conversation" at Inventors Brewpub on September 10. A Town of Port resident described braking hard every day as workers turned from Lake Drive onto Highway LL. Ramon Perez, Vantage's environment, safety and health manager, said roughly 800 construction workers and the construction equipment use the campus entrance on Highland Drive. He said he would talk with workers about following traffic rules, Ozaukee Press reported.

Vantage lists campus construction hours as 6 a.m. to 8 p.m., Monday through Saturday. Saturdays count as work days on the north side too.

Who Pays When the Roads Wear Out

Heavy trucks on county highways bring up an obvious question about repaving. In June, the Common Council approved an agreement with Ozaukee County that lets the county repair any city street, town road or county highway near the campus damaged by the project and bill Vantage directly. Mayor Ted Neitzke said the city's development agreement with Vantage also requires the company to pay for any needed roadwork, according to Ozaukee Press. The same agreement covers the temporary intersection work and the ramp signals.

For a specific construction or safety concern, Vantage's construction updates page lists a contact address, [email protected], and posts road notices such as the August pavement patching on County Highway A and the Union Pacific closure of the Highway KW railroad crossing from August 31 to September 4.

What Comes Out After Construction, and What Stays

Once the campus is finished, the temporary signals and wider intersections are scheduled to come out, with Vantage handling the removal. Motl told aldermen the Exit 100 lights would stay through construction, which is expected to wrap up in 2028. At its September update, Vantage reported two of the four buildings enclosed and in interior work, with crews still putting up the frames of the other two.

Other work tied to the project falls under a separate arrangement. When the Vantage land was annexed from the Town of Port Washington into the city, the city agreed to extend sewer and water into the town's Knellsville area. That means new lines to Highway KW, Mink Ranch Road and Highland Drive near the Port Town Hall. As of June, that project was waiting on Public Service Commission approval before going out to bid. The intersection changes are scheduled to come out, while the utility lines are a city obligation from the annexation deal.

Oracle's Beatrice Fullan said the September 10 event was the first of several "community conversations." Future sessions are the natural place to ask when the Highland Lane and Lake Drive widenings will be reversed and what Highway LL will look like after that.

If you own a home along Highway LL, Lake Drive or Highland Lane and want to know how buyers will see these changes, between now and 2028 and after the hardware comes out, The Cottrell Team can walk the property with you. Jared's construction background helps him separate what's temporary from what's permanent, and the team will put an honest number on it. Request a Complimentary Market Valuation.